|
The construction of the project, with
the exclusion of the pavement installation, was
competitively bid by our facilities group. The contractor
selected for this portion of the work was Scott
Construction. Scott commenced construction on 17 September
2007.
The contractor selected for the
placement of the pervious concrete was Engelman
Construction. This firm was recommended by Mr. Phil Kresge
of the NRMCA. Mr. Kresge worked closely with Engelman
Construction, a certified pervious concrete contractor, to
develop a mix design and was present for the placement of
the pavement. The pervious concrete was placed on 8 and 9
October 2007. A summary of the installation process is
presented below:
The pervious concrete installation at
Villanova University was carried out over two 4-hour days,
with a 15’x50’ area being poured each day. The process
began with setting up forms and spraying them with a diesel
fuel lubricant. While the forms were being set up the stone
bed was wetted thoroughly so that the concrete would not dry
too quickly and crack after being laid. Once the gravel was
soaked, the concrete was poured from a mixer to cover an
approximately 15’x7’ area at a depth of 6”. A 3 person crew
spread this concrete to approximately level using hand
shovels and rakes. Next, another 3 person crew ran a 16’
long roller screed, lubricated with diesel fuel, over the
poured area to level the concrete. Finally, a tarp was
pulled over the finished area to prevent quick drying. This
tarp must be placed over the finished area within 15 minutes
of the concrete mix leaving the mixer to ensure successful
results. This process was then repeated until the entire
15’x50’ area was poured and leveled. Two evenly spaced
control joints were grooved in the fresh concrete across the
50’ dimension to allow for expansion of the concrete.
After the first half of the bed was
poured, it was allowed to cure for one day before the second
half of the bed was poured. This was to allow the first half
to harden enough for the crew to walk and run the end of the
roller screed over. At the completion of the two pours, the
concrete was cured with the tarp still covering it for one
week before it was open for traffic.
The contractor selected for the
placement of the porous asphalt was Burkholder Pavement.
This firm was recommended by Mr. Kent Hansen of NAPA. The
mix design was created by Cahill Associates and is the same
material placed at the Radnor Township Middle School in
Wayne, PA (about 5 miles west of Villanova). The porous
asphalt was placed on 1 October 2007.
The installation of the asphalt
occurred in one day and took approximately three hours to
complete. A team of five used standard asphalt equipment
and procedures in the installation. The standard asphalt
procedure uses an asphalt paver which can hold large
quantities of the hot asphalt. This paver spreads a level
strip of asphalt that is approximately eight feet in length.
The depth of the asphalt was 2.5 inches. For the tight areas
and the edges where the paver could be used the asphalt was
placed by hand. Part of the standard installation procedure
is using diesel fuel as a lubricant on the equipment to
prevent the hot asphalt from sticking to the rakes and other
pieces of equipment, and allowing for the even distribution
of asphalt throughout the site. Consequently, the spraying
of diesel fuel over the site was done quite frequently over
the course of the installation. After the asphalt was laid a
mechanical roller was used to compact the asphalt surface.
The result of this compaction left some small areas where
there is no visible pore space. These areas are small and
sporadically spaced, and should not affect the overall
performance of the asphalt surface.
Approximately two weeks after the
completion of the asphalt installation a hot tar seal was
applied to the edges of the asphalt site. This is to help
prevent any spalling from occurring from the edges, and help
strengthen the joint between the standard and porous
asphalt. The hot tar seal covers no more then six inches of
the porous asphalt.
|