On Campus BMP Research
Villanova Porous Asphalt BMP
 
 

Design Components

 

Report on Construction of Porous Pavement in Pavilion Parking Area
Villanova University

William Heasom, July 13, 2006

Introduction

A porous asphalt parking area (20 spaces) was constructed behind the Pavilion at Villanova University as part of an extensive parking area renovation. The area covered with porous pavement is shown (hatched) in Fig. 1.


Figure 1

During construction, representatives of Villanova University Urban Stormwater Partnership (Emerson, Benford, and Heasom) were onsite to observe the construction of the porous asphalt and to make measurements of the prepared subgrade prior to the paving operation. This was done so that the observed performance of the pavement/storage bed/infiltrating subgrade may be understood in terms of the soils underlying the improvement as well as the geometry of the installation.

Site Observation and Measurements

The contractor for this project is Nason Construction and the paving subcontractor responsible for the porous asphalt is H & K Group. Early on June 6, 2006, the H & K had established the subgrade for the porous parking area and was ready to begin placing the rock for the storage bed. Figs. 2 shows the site just before the placement of the storage bed rock and Fig. 3 shows the rock being placed. Leo Kob of Villanova facilities pointed out some pieces of filter fabric still embedded in the subgrade (Fig. 4) which are remnants from the previously existing parking area there, and the very compact nature of the subgrade was noticeable. It was decided that, since this project is an experiment and since there is value learning from installations done under “real world” conditions, the placement of the pavement should continue without attempting to address some of the shortcomings of the prepared subgrade.


Figure 2


Figure 3


Figure 4


Figure 5


Figure 6

A series of four infiltrometer measurements were made and bulk density samples were taken. The double ring infiltrometer can be seen in Fig. 5 and the locations and infiltration results can be seen in Fig. 6 with a tabular summary in Table 1.


Table 1

At this time, a series of elevation measurements were made of the subgrade and of the top of the existing curb (Fig. 6). The pavement and curb cross section is given in Fig. 7.

During rainfall events, surface water will flow from the tributary areas (to be determined) around the pervious parking area and join with the rain falling directly on the pervious pavement surface to fill the void volume in the rock storage bed. A portion of this inflow will be rapidly infiltrated, with the rest stored and infiltrated more gradually over time. When the cumulative inflow exceeds the storage volume, the system will surcharge and deliver the overflow to the central inlet at the surface. Two PVC pipes were installed during construction to serve as auxiliary drains and as access points for a pressure transducer so that the level of water in the storage bed may be measured during storms. The elevation measurements taken during construction allow the development of the storage volume and wetted area vs. storage volume relationships that are essential to understanding the behavior of the system during rainfall events. The contours interpolated from these elevation measurements are shown in Fig. 8 and the derived stage-storage and stage-wetted area relation is given in Table 2.


Figure 7


Figure 8


Table 2