|
The design
engineering for this project was done by
Cahill
Associates, West Chester PA.
The pervious
concrete site is located in a courtyard between two
dormitories, Sheehan and Sullivan Hall. This area is known
as the "Quad". The Quad renovation project was initiated to
create an aesthetically pleasing courtyard that functioned
as a Stormwater Infiltration Best Management Practice (BMP).
Figures 1 & 2 show the Quad and the surrounding area as it
was prior to the renovations.
Figure 1: A sketch of the Quad prior to construction.
Figure 2: A pre-construction photo of the Quad.

Stormwater
History and Background
The pervious
concrete site is designed to infiltrate small volume storms
(1-2"). From these smaller events, there is essentially no
runoff from the site. In this region, infiltration of the
two inch storm event accounts for approximately 95% of the
total annual precipitation. This BMP provides groundwater
recharge and helps maintain baseflows of nearby first order
streams.
The pervious
concrete is outlined with decorative pavers. The pavers
divide the pervious concrete into three separate sections as
seen in Figure 3. Below these three sections are individual
storage beds. Since the site lies on a significant slope it
was necessary to create earthen dams that isolate each
storage area. At the top of each dam there is an overflow
pipe which connects the storage area with the next
downstream. The final storage bed has an overflow that
connects to the existing storm sewer. The beds are
approximately 4 feet deep and are filled with a #4 stone,
producing about 40% void space within the beds. A geotextile
liner was laid down to separate the storage beds from the
undisturbed soil below. The liner's primary function is
separation. The idea is to avoid any upward migration of the
in-situ soil, which could possibly reduce the capacity of
the beds over time. (See Figure 7 & 8).
Figure 3: Architectural Concept Drawing

The
Infiltration/Storage Area table below breaks down the three
infiltration beds into their respective runoff volume
capacities. The beds illustrated below in Figure 4. The
three beds can hold approximately 9,700 ft3 (725,000
gallons) of stormwater runoff can be stored for
infiltration. This capacity of the beds coupled with well
draining characteristics (k = 1.67 x 10-4 cm/s) of the
underlying soils presents a very promising situation where
infiltration of the smaller storms can be easily
accomplished. A cross section and longitudinal profile of
the infiltration beds are illustrated in Figure 5 and 6
respectively.
Figure 4:
Conceptual drawing of the Infiltration Bed locations


Figure 5:
Cross-section of the Stormwater Recharge Bed.

Figure 6: Longitudinal Profile of the
Stormwater Recharge Bed

Figure 7: A photo of the lower storage
bed

Figure 8: Middle storage bed under
construction. Notice the earthen berm and lower storage bed
at the far right of the frame

The contributing drainage area for the
site is about 65,000 square feet and is approximately 40%
impervious. The roof drains of both adjacent dorms are tied
into the storage beds. A rough outline of the watershed is
illustrated below. During a storm event, any rain that falls
within the outlined area will eventually make its way into
the infiltration beds. The Runoff Volume table below shows
the expected runoff volumes for a 2-year storm broken down
into the major components that make up the Quad. It should
be noted that almost half of the contributing runoff volume
is from the roof tops. The roof drains are connected to an
underground system of conduit and run directly to the
infiltration beds.
Figure 9: Contributing drainage area


Figure 10: Completion of bed
construction by covering with choker stone prior to pouring
of the pervious concrete

Reconstruction/Redesign
The original construction of the Pervious
Concrete Infiltration BMP site began in May of 2002 and was
completed in late August. Through the course of
construction, there were a number of different elements that
lead to the ultimate failure of the surface of the pervious
concrete. The failed surface is illustrated in Figures 11 &
12. The site was redesigned and reconstructed in May of
2003.
Figure 11: Extensive patching of
pervious concrete. Notice color differentiations.

Figure 12: Failure of the pervious
concrete surface. Notice the abundance of loose gravel.

Many lessons were learned from the
initial construction which were taken into consideration in
the redesign and construction. The key areas that led to the
eventual failure of the surface were: environmental factors,
material inconsistencies, and inadequate finishing methods.
Environmental factors made the installation extremely
difficult. High temperatures made the mixing process
unpredictable and caused the curing process to occur too
quickly. Inconsistencies in the concrete mixture from one
truck to truck became an issue. Mixing time in the trucks
varied as did travel time to the site. This increasing the
amount of time the concrete spent sitting in the trucks.
This worked to reduce the already small workability window
of the material. The finishing technique used was also found
to be inadequate. The use of a vibratory screed to spread,
level, and compact the material proved to be insufficient. A
modified plate tamper was tried next but was also found to
do a poor job. The finished surface was uneven and rutted in
some spots. Attempts to fix the bad spots often resulted in
making the areas worse and were quickly abandoned.
During the reconstruction, many issues
were rectified. The extremely high temperatures were
combated by starting the project earlier in the summer when
the conditions and temperatures were more favorable. Removal
of the failed material began in late-May with construction
being completed in early June, before it started getting
hot. To eliminate inconsistencies in the material, it was
determined that water would be added on site once the trucks
arrived. Mixing would also take place on site so that it
could be closely monitored. For compaction and finishing it
was found that a 50 gallon plastic drum filled with water
gave the best results.
From initial data and observations of the
site it was determined that the original design had more
than enough pervious concrete area and this area could be
decreased without effecting the site’s performance. A new
layout was designed which included small strips of pervious
concrete around the perimeter, with standard concrete
replacing the pervious concrete in the middle of the
walkway. The regular concrete was crowned to drain toward
the pervious strips on the perimeter.
Figure 13: Artist's rendering of new
pervious concrete design. The pervious concrete is
represented by the dark grey strips.

Instrumentation
In addition to the surface water
hydrology, there is an interest in seeing what happens to
the water once it infiltrates through the pervious concrete
and enters the infiltration beds. To help understand what
takes place, a number of different instruments have been
installed. Figure 14 below is an illustration of a lysimeter.
This instrument is used to extract water samples,
representative of the respective storm events, from the soil
beneath the infiltration beds. Figure 15 shows a lysimeter
prior to installation and Figure 16 shows the lysimeters
already installed. Note the tubes extending from the three
lysimeters. The tubing runs through conduit to a utility box
parallel to the site where the samples can be pumped out
into sample containers.
Due to the size of the drainage area and
lack of point source pollution, very little in the way of
contaminants are expected. Villanova has always taken pride
in maintaining the most beautiful landscape possible. To
accomplish this, fertilizers containing Nitrogen and
Phosphorous are used. Testing has begun to look for the
presence of these two elements. The industry standard for
septic tanks has always been that the waste water is
cleansed after 4 feet of infiltration. This same approach
was applied to the infiltration system in the Quad. The
lysimeters were placed at depths of 1, 2 and 4 feet beneath
the base of the infiltration beds at two locations, the
opposite corners of the lower infiltration bed. Two
lysimeters were also placed outside of the lower
infiltration bed on the Sheehan side of the Quad. They were
placed at depths corresponding to the 1 foot and 4 foot
lysimeters in the bed. These lysimeters will be used to
obtain "untreated" values. The results of the water quality
tests should help to support the industry standard.
Tests are also being conducted for
Hexavalent Chromium, Copper, and Zinc. It is believed that
these values will be less prevalent than Total Nitrogen and
Total Phosphorus. Once sufficient background testing has
been completed, it is possible that some of these tests may
be eliminated due to insignificant values.
Figure 14: A sketch of a lysimeter in the
ground

Figure 15: A lysimeter prior to
installation

Figure 16: Layout of the lysimeters
under the lower bed. The tubes allow air and water samples
to be pumped out.

The moisture fronts resulting from the
infiltrated rainfall runoff are also being monitored as they
pass through the soil strata. Moisture meters, as
illustrated below in Figures 17, 18, and 19, have been
installed in close proximity to the lysimeters. The layout
of the moisture meters mirrors that of the lysimeters. They
are spaced at 1, 2, and 4 foot depths at opposite corners of
the lower infiltration bed. The data collected from the
moisture meters will aid in a number of different aspects of
the research. One of the benefits of these instruments is
that they can help to determine the rate at which the water
is being infiltrated.
Figure 17: A moisture meter with installation tool
used to ensure proper spacing of the prongs.

Figure 18: A close-up picture of moisture
meters in the soil wall

Figure 19: Spacing of the moisture meters outside the
lower infiltration bed

A tipping bucket rain gauge was mounted
on the roof of Bartley Hall. A v-notched weir was
constructed in the storm drain on the Sullivan Hall side of
the Quad directly below the lower infiltration bed. A
pressure transducer probe was mounted upstream of the weir.
The probe measures the depth of water behind the weir which
can then be converted to a flow. This is an accurate
measurement of the overflow from the infiltration beds.
Figure 20: Tipping bucket rain gauge.
Notice the bird deterrent wire.

Figure 21: V-Notched weir in the storm
drain. Plexiglas cover used to separate ground runoff from
infiltration bed overflow.

To accurately measure the depth of water
in the lower infiltration bed, another pressure transducer
probe was placed in the junction box directly upstream of
the overflow storm drain. The bottom of the junction box is
at the same elevation as the bottom of the lower
infiltration bed, therefore the depth of the water in the
junction box is the same as in the infiltration bed. This
data is helpful in determining infiltration rates from the
lower bed. |